May 2024 Scroll down For this Month
________
5/31/2024
![](CLEANING.jpg)
Clean Up
________
5/30/2024
![](BCS119.jpg)
First Coat of Paint Inside
________
5/29/2024
![](BCS118.jpg)
Sheet Rock Taped and Mudded
__________________
5/27/2024 - 5/28/2024
![](cleaning2.jpg)
Clean Up
________
5/26/2024
![](BCS117.jpg)
All the Sheet Rock is Up
________
5/25/2024
![](BCS116.jpg)
Sides and Ceiling Sheet Rocked
________
5/24/2024
![](cleaning2.jpg)
Clean Up
________
5/23/2024
![](Garden52324a.JPG)
Worked in Garden 80% Planted
________
5/22/2024
![](Garden52224a.JPG)
Worked in Garden
________
5/21/2024
![](DimBulb.JPG)
Rest Day, Made a Dim Bulb Load Tester
________
5/202024
![](Mow52024.JPG)
Mow
________
5/19/2024
![](BCS115.jpg)
Outside Washed and Painted
________
5/18/2024
![](BCS114.jpg)
All the Aluminum Siding is On
________
5/17/2024
![](BCS112.jpg)
Caulked, Wrapped and West Side Covered with Aluminum, (Dirty Now)
________
5/16/2024
![](BCS109.jpg)
All the Siding is Up
________
5/15/2024
![](BCS108.jpg)
Roof is Finished
________
5/14/2024
![](BCS107.jpg)
Sorted Aluminum Sheeting, Cut to Size for Roof at BCS
________
5/13/2024
![](BCS106.jpg)
Some Plywood Up
________
5/12/2024
![](BCS105.jpg)
Stripped More Concrete Forms Apart
Moved Some Plywood Up The Hill
________
5/11/2024
![](cleaning2.jpg)
Clean Up Day
________
5/10/2024
![](BCS104.jpg)
Framing is Finished
________
5/09/2024
![](BCS103.jpg)
Three Stud Walls Done
________
5/08/2024
![](BCS102.jpg)
North Wall Framed
_______
5/072024
![](BCS101.jpg)
Move Lumber and Tools Up the Hill,
Attached Bottom Plate to Mud Sill
________
5/06/2024
![](PottingSoil5624.jpg)
Process Compost and Made Potting Soil
________
5/05/2024
![](cpu_problems.jpg)
Computer Wars Continue________
5/04/2024
![](COMPUTERJUNK.jpg)
Sorted Old Computer Junk
________
5/03/2024
![](Office_a_10_31_15.jpg)
Cleaned Office
________
5/02/2024
![](cpu_problems.jpg)
Computer Wars
________
5/01/2024
![](BCS100.JPG)
Took Apart Forms and Moved Lumber to BCS